 Peremajaan Jalan Lingkungan di Empat Pulau Permukiman Mencapai 25 Persen

Collector Road Maintenance Process in Four Islands Reaches 25 Percent

As long as 17 thousand meters collector roads in four islands of Thousand Islands are currently under maintenance. Its process currently reaches 25 percent.

We hope this project could finish in December

Thousand Islands Technical Work Unit (UKT) 2 Head, Sofyan mentioned, collector road maintenance is done in Tidung Island, Untung Jawa Island, Panggang Island, and Pramuka Island. This collector road maintenance project has been started since August.

"Until now, its process reaches 25 percent," he added, Tuesday (10/1).

Until December, Bina Marga Targeted to Concrete 107 Collector Roads in North Jakarta

He explained, 50 percent of building material used to repair the collector roads have been transported to the location. His side still has three months left to complete road maintenance.

In detail, there are 1,000 meters collector roads in Panggang Island; 9,000 meters in Pramuka Island; 2,000 meters in Tidung Island; and 5,000 meters in Untung Jawa Island that need to be repaired.

"We hope this project could finish in December," he stated.

Linked News
Popular News indeks
  1. Open for All: Jakarta City Hall Welcomes Visitors for Namu Balai Kota

    access_time03-10-2026 remove_red_eye713 personDessy Suciati
  2. Transjakarta Reaffirms Ban on Busking in Mikrotrans and Bus Stops

    access_time02-10-2026 remove_red_eye530 personAldi Geri Lumban Tobing
  3. Jakarta Builds Five New Animal Health Centers to Expand Veterinary Services

    access_time30-09-2026 remove_red_eye529 personAldi Geri Lumban Tobing
  4. 1,500 Runners and Pets Hit the Track for World Rabies Day Run 2026

    access_time03-10-2026 remove_red_eye518 personAnita Karyati
  5. Commission D Supports Reserve Fund for Long-Term Infrastructure

    access_time02-10-2026 remove_red_eye504 personFakhrizal Fakhri